Drain Commissioner

Current Projects

Black Creek Intercounty Drain:

  • Petition received on 08-15-06
  • Drainage Board met for the Determination of Practicability on 10-19-06 and petition was found practicable
  • Engineer was selected on 12-07-06
  • Hearing of Necessity took place on 12-15-08 and project was found to be necessary
  • An appeal against the Determination of Necessity was filed by Spencer and Nelson Townships on 12-23-08

Kenowa Drain:

  • Petition being circulated
  • Drain Office meeting with the City of Walker on 03-12-09 to discuss possible solutions
  • Scheduling Drain Board Meeting to Determine Necessity

Shawmut Hills Drain:

  • Petition received 08-26-08
  • Board of Determination met on 06-02-09 and found project to be necessary

Troy with Mosher and Farnham Drain:

  • Petition received on 05-20-09
  • Scheduling Board of Determination

Waters Drain:

  • Petition received on 05-07-07
  • Board of Determination met on 01-17-08 and found project to be necessary
  • Engineer was selected on 03-10-08
  • DEQ Permit Application submitted on 01-30-09
  • Bids received 06-01-09
  • Day of Apportionment scheduled for 06-29-09
  • Project Summary
  • Drainage District Map
  • Under Construction

Warner Drain:

  • Petition received on 07-02-08
  • Board of Determination met on 01-15-09 and found project to be necessary
  • Request for Proposals from Engineers was sent out on 01-23-09
  • Proposals due from Engineers on 03-06-09
  • Stream survey complete
  • Engineer Designing Drain Improvements