Information You Need

Construction Progress

Click thumbnail for a larger image.

2008

July
Concrete topping over precast slab (basement area) - 1st floor. Basement Concrete Poured. Roofing materials delivered to site for installation. Roofing Material Delivered.
North entry lobby slab on grade, in-floor heat loop. North Entry. Penthouse exterior stud wall framing. Exterior Stud Wall Progress.
Spiral ductwork installation - 2nd floor. 2nd Floor Ductwork. 3rd floor bathroom plumbing. 3rd Floor Bathroom Plumbing.
Electrical ductbank, North. Electrical ductbank, North. Insulation, in-floor heat & slab on grade pour. Insulation, in-floor heat & slab on grade pour.

June
2nd floor slab. 2nd floor slab. Building north view, entry canopy. Building north view, entry canopy.
Building south west view. Building south west view. Ductwork in progress. Ductwork in progress.
Stair two steel being installed. Stair two steel being installed. Stair three concrete treads. Stair three concrete treads.
Steel joist and roof decking. Steel joist and roof decking. Under slab plumbing rough-in, 1st floor. Under slab plumbing rough-in, 1st floor.

May
Metal decking on 2nd floor. Metal decking on 2nd floor. Piers & footings for main entrance canopy. Piers & footings for main entrance canopy.
South lot curb & gutter. South lot curb & gutter. South lot retaining walls. South lot retaining walls.
South west section of building. South west section of Building. Steel erection. Steel erection.
Structural steel erection continues. Structural steel erection continues. West stair towers. West stair towers.

April
Basement steel erection. Basement Steel Erection. Basement steel erection. Basement Steel Erection.
Elevators E1 & E2 masonry work. Elevators E1 & E2 masonry work. Footings for emergency gen set, fire pump area. Footings for emergency gen set, fire pump area.
Structural steel delivered on site. Structural steel delivered on site. Structural steel erection. Structural steel erection.

March
Earth retention system. Earth retention system. Earth retention system. Earth retention system.
Footing excavation, resteel & formwork. Footing excavation, resteel & formwork. Formwork & resteel for basement walls. Formwork & resteel for basement walls.
Freight elevator pit excavation, resteel placement. Freight elevator pit excavation, resteel placement. Sanitary line tie-in at Jefferson Avenue. Sanitary line tie-in at Jefferson Avenue.
South lot water retention drainage system. South lot water retention drainage system. South lot water retention drainage system. South lot water retention drainage system.

2007

December
Demolition of existing building. Demolition of existing building. Demolition of existing building. Demolition of existing building.