Information You Need

Construction Progress

Click thumbnail for a larger image.

2009 Construction

May
North Entry - Snowmelt System NW Parking Lot
Picnic tables, umbrellas and benches installed North and South Parking Lots
Secured Parking Gate Installed Basement High Density Filing
North Entry Canopy South Elevation - KCHSC Sign Installed

 

April
Southwest Elevation Snowmelt System for Sidewalk Concrete
Excavation of NW Parking Lot North Driveway at Loading Dock

 

March
Southwest Elevation Installation of Toilet Partions in Progress
Freight Elevator E-3 Work in Progress IT Closet - 3rd Floor
Finishes on 2nd Floor - Electrified Furniture Connections, Paint, Carpeting, etc. Penthouse Misc. Electrical Panel Work
Wall Guards and Carpet Installed on 1st Floor Rooms North Elevation

 

February
Installed Ceiling Clouds and Light Fixtures on 1st Floor North West Corridor Above Ceiling Pipe and Valve Labelling
Above Ceiling Rough-in on 2nd Floor North East Corridor Plumbing Fixtures installed on 2nd Floor
Prep Work for Ceiling Clouds on 2nd Floor Ceiling Tiles, Light Fixtures Installed on 2nd Floor
Ceiling Grids, Duct Work, Stored Material, etc for the 3rd Floor South West Elevation

 

January
Triming & detailing of north curtain wall Elevators E-1 & E-2 work in progress
First floor bathroom fixtures Installation of Kitchen equipments in progress
Triming & detailing of north curtain wall Elevators E-1 & E-2 work in progress
First floor bathroom fixtures Installation of Kitchen equipments in progress

2008 Construction

December
Drywall finish - 1st floor north corridor Quarry tile installed for 1st floor Employee Bathroom
Cooler installed in Kitchen Casework installation - 1st floor
Drywall finishes on 2nd floor 3rd floor drywall stud framing and installed door frames
Ductwork continues in the Penthouse Piping connection to chiller

 

November
Drywall Finish - 1st Floor Mechanical Room - Penthouse
Stud Wall Framing - 3rd Floor Access Flooring Installation - 3rd Floor
South Elevation with Brick Piers Insulation of Drywall and Stud Walls on 1st Floor
Access Flooring on 2nd Floor Paving Northeast Porous Pavement

October
Northeast lot - fine grading for porous paving North curtain wall
Southwest corner of building Southeast corner of building
Mechanical Penthouse - work in progress Removal of concrete rubble encountered
Drywall framing, electrical rough-in, wood blocking Masonry brick wall - West elevation

September
East brick wall completed Chiller set in the enclosed screen wall
Misc. piping installation in progress South lot landscaping - trees & shrubs planted
Metal wall panels installed at the Penthouse Curtain wall frame installation
South lot mini mesh fence installed First floor interior stud wall framing & NW brick wall

August
Roofing Installed. Basement Concrete Poured. Delivery of Chiller to site. Roofing Material Delivered.
East Wall - Exterior Stud Framing at Window Openings. North Entry. Started Brick Wall Installation. Exterior Stud Wall Progress.
Interior 2nd Floor Column Enclosure Framing. 2nd Floor Ductwork. Rough-in Work in Progress on 3rd Floor - Duct Work, Piping. 3rd Floor Bathroom Plumbing.
Penthouse Equipment Pads Poured. Electrical ductbank, North. South Lot Paving - 1st course. Insulation, in-floor heat & slab on grade pour.

July
Concrete topping over precast slab (basement area) - 1st floor. Basement Concrete Poured. Roofing materials delivered to site for installation. Roofing Material Delivered.
North entry lobby slab on grade, in-floor heat loop. North Entry. Penthouse exterior stud wall framing. Exterior Stud Wall Progress.
Spiral ductwork installation - 2nd floor. 2nd Floor Ductwork. 3rd floor bathroom plumbing. 3rd Floor Bathroom Plumbing.
Electrical ductbank, North. Electrical ductbank, North. Insulation, in-floor heat & slab on grade pour. Insulation, in-floor heat & slab on grade pour.

June
2nd floor slab. 2nd floor slab. Building north view, entry canopy. Building north view, entry canopy.
Building south west view. Building south west view. Ductwork in progress. Ductwork in progress.
Stair two steel being installed. Stair two steel being installed. Stair three concrete treads. Stair three concrete treads.
Steel joist and roof decking. Steel joist and roof decking. Under slab plumbing rough-in, 1st floor. Under slab plumbing rough-in, 1st floor.

May
Metal decking on 2nd floor. Metal decking on 2nd floor. Piers & footings for main entrance canopy. Piers & footings for main entrance canopy.
South lot curb & gutter. South lot curb & gutter. South lot retaining walls. South lot retaining walls.
South west section of building. South west section of Building. Steel erection. Steel erection.
Structural steel erection continues. Structural steel erection continues. West stair towers. West stair towers.

April
Basement steel erection. Basement Steel Erection. Basement steel erection. Basement Steel Erection.
Elevators E1 & E2 masonry work. Elevators E1 & E2 masonry work. Footings for emergency gen set, fire pump area. Footings for emergency gen set, fire pump area.
Structural steel delivered on site. Structural steel delivered on site. Structural steel erection. Structural steel erection.

March
Earth retention system. Earth retention system. Earth retention system. Earth retention system.
Footing excavation, resteel & formwork. Footing excavation, resteel & formwork. Formwork & resteel for basement walls. Formwork & resteel for basement walls.
Freight elevator pit excavation, resteel placement. Freight elevator pit excavation, resteel placement. Sanitary line tie-in at Jefferson Avenue. Sanitary line tie-in at Jefferson Avenue.
South lot water retention drainage system. South lot water retention drainage system. South lot water retention drainage system. South lot water retention drainage system.

2007 Construction

December
Demolition of existing building. Demolition of existing building. Demolition of existing building. Demolition of existing building.