Human Services Complex

Proposed Site Plan Proposed Site Plan
South Parking Lot South Parking Lot

Facility Facts

  • 137,000 square feet Three (3) floors On-site parking spaces, with additional on-street parking available
  • LEED Certified - U.S. Green Building Council’s Leadership in Environmental & Energy Design, including:
    • Energy Efficient Mechanical/Electrical Systems
    • Expansive Use of Glass
    • Reflective Roof
    • Water Reduction Systems
    • Permeable Asphalt - Reduces Storm Water Discharge
    • Low Maintenance Landscaping
    • Locally Made Products/Components
  • $27 Million investment in the community - hundreds of construction jobs + 400 Department of Human Services, ACSET, and Health Clinic employees
  • Design Plus - Architects/Engineers
  • The Christman Company - Construction Managers
  • Groundbreaking: October 29, 2007
  • Construction: November 2007 to May 2009
  • Occupancy: June 1, 2009